Reorder point: formula, example and how to keep it current.

The reorder point is the stock level at which you place a new order with the supplier. It equals average daily usage times lead time, plus safety stock.

What a reorder point is

The reorder point answers one question: at how many units on the shelf should I order. Order later and you risk running out. Order earlier and money sits in the warehouse.

Without it, orders are placed by eye or when someone notices an empty shelf. That works with ten items, not with several hundred.

The point is set for each item separately. For a warehouse with many items, it turns “when should I order” from a feeling into a rule.

It works best for materials and goods with fairly steady usage. Items you buy only against a specific customer order follow different logic.

The formula

Reorder point = average daily usage × lead time in days + safety stock.

  • Average daily usage: how many units leave the warehouse per working day.
  • Lead time: how many days pass from placing the order until the goods are on the shelf.
  • Safety stock: a buffer for days with higher usage or a late delivery.

The first part covers normal usage while you wait for the delivery. Safety stock covers the surprises.

If the item is also used on Saturdays, use calendar days everywhere. What matters is that usage and lead time are in the same unit.

If the supplier only delivers on certain days, add the days of waiting for the next delivery day to the lead time.

How to find the numbers

Average daily usage comes from history. Take the quantity issued over the last three months and divide it by the number of working days.

Lead time isn’t what the supplier promises. It’s the real time from your order to booking the goods in, including days the order waits for approval.

There are statistical formulas for safety stock, but a simple rule is enough to start. Take the difference between the longest and the usual lead time and multiply it by average daily usage.

Use working days for both usage and lead time. Mixing calendar and working days is a common mistake.

Leave unusual periods out of the history. A one-off large order, for example, or a week when the shop floor was stopped.

If you have several suppliers for one item, use the lead time of the one you order from most often. With no history, start from the sales team’s estimate and check it after a month.

Step-by-step example

For example, a packaging company uses board for cartons. The numbers are hypothetical.

  1. Over the last three months, or 60 working days, 2,400 sheets were issued. Average daily usage is 2,400 ÷ 60 = 40 sheets.
  2. Delivery usually takes 7 working days, and the longest delay so far was 10 days.
  3. Safety stock: (10 − 7) × 40 = 120 sheets.
  4. Reorder point: 40 × 7 + 120 = 280 + 120 = 400 sheets.

When stock falls to 400 sheets, you place an order. Over the seven days of waiting you’ll use about 280. That leaves 120 for surprises.

Sanity check: 400 sheets cover 10 working days of usage. That is exactly the longest lead time you’ve seen so far.

Compare that with ordering by eye. If the storekeeper orders at two pallets, say 300 sheets, the first delay will stop the shop floor.

If next month usage rises to 50 sheets a day, the point becomes 50 × 7 + 150 = 500. That’s why it gets recalculated regularly.

The reverse holds too. If usage falls to 30 sheets a day, the point becomes 30 × 7 + 90 = 300, and less money sits in the warehouse.

The point says when, not how much

The reorder point sets the timing. How much to order is a separate question that depends on the supplier’s minimum order, discounts and warehouse space.

A simple rule to start: order the usage for a period that suits you. Two or four weeks, for example. That keeps the level after delivery predictable.

For example, at 40 sheets a day and an order covering 20 working days, the quantity is 800 sheets. After delivery stock will be about 120 + 800 = 920 sheets.

If the supplier’s minimum order is 1,000 sheets, you order 1,000. The next order then simply comes a little later.

The less often you order, the more money sits in stock, but the less time ordering takes.

Common reorder point mistakes

  • Lead time taken from the quote instead of measured.
  • Average usage from a year with very different sales.
  • One point for every item, “100 of each”.
  • Safety stock that grows after every delay and never shrinks.
  • A point compared with a stock level that isn’t accurate.

The last mistake is the sneakiest. If the system thinks you have 500 and the shelf holds 350, the alert comes too late.

How to keep it current

A reorder point isn’t a number you calculate once. It follows sales, suppliers and the season.

An alert is useless if nobody owns it. Decide who checks it and places the order the same day.

The formula is only as good as the stock level you compare it with. If the warehouse numbers aren’t right, start with real-time inventory.

How we approach it

In Leanovix every item has a minimum quantity per warehouse. When stock drops below it, you see it at once on the dashboard and in the warehouse. Notifications and suggested purchase orders we build around your process, on request. See the inventory module and the purchasing module.

Frequently asked questions

How do you calculate a reorder point?

Multiply average daily usage by lead time in days and add safety stock. For example, 40 units a day × 7 days + 120 units of buffer = 400 units.

What is the difference between reorder point and safety stock?

Safety stock is the buffer for surprises. The reorder point includes it, plus the usage while you wait for the delivery.

How often should I recalculate the reorder point?

At least once a quarter, and straight away for seasonal items or a change of supplier. If the system calculates it from history, it can update automatically.