Production planning: from orders to a realistic schedule.

Production planning answers what gets made, when and on which machine, so that promised dates are met. It starts with capacity in hours and available materials, not with a long list of orders.

What production planning is

A plan spreads orders over time according to the capacity of people and machines. A good plan also shows when each order will be finished.

In small companies the plan is often a whiteboard or a spreadsheet one person understands. That works while orders are few. As you grow, delivery dates start being promised on gut feeling.

Planning has two horizons. The weekly plan spreads orders over days and machines. The daily plan tells the shop floor exactly what to do today and in what order. Both should be visible in one place.

What you need before you plan

  • Open orders with quantities and promised dates.
  • The bill of materials and routing for every product.
  • Material stock and expected deliveries.
  • Capacity of every machine or workstation in hours.

If any of these is missing, the plan is a guess. The routing is most often missing: nobody wrote down how long each operation takes. More on that in the article on the bill of materials.

If times aren’t written down anywhere, start with the foreman’s estimate. Two weeks of shop floor reports will show where the estimate holds and where it doesn’t. A rough number beats no number, as long as you correct it.

Capacity in hours, not units

Capacity is measured in hours because different products occupy a machine for different lengths of time. A thousand small parts and a hundred large ones can take the same time.

The routing turns an order into hours: quantity times time per unit, plus set-up time. For example, 1,200 parts at 1.5 minutes each plus half an hour of set-up is 30.5 hours.

Count available hours realistically. Subtract breaks, set-ups, planned maintenance and the usual stoppages from each shift. If you plan with the full eight hours, the plan is behind from day one.

Mark the bottleneck: the machine or team that’s always fully loaded. The pace of the whole operation depends on it.

If you don’t know your usual stoppages, start with a 15–20% buffer per shift and adjust after a month of reports. The number will be yours, not one from a textbook.

Example: one press and three orders

For example: a shop runs two shifts with 7.5 productive hours each. The press has 15 hours a day, or 75 hours a week. The numbers are hypothetical.

  • Order A: 30 hours on the press, due Friday.
  • Order B: 25 hours, due Thursday.
  • Order C: 28 hours, due Friday.

That’s 83 hours against 75 available. Not everything due by Friday fits. The options are clear: an 8-hour Saturday, moving part of C to another machine, or a new date agreed with the customer today.

What matters is that you see this on Monday, not on Thursday evening. The conversation with the customer is much easier when it happens in time.

If C can be split, 20 hours get done by Friday and 8 hours move to Monday. The customer gets most of the order on time and the rest on a clear date.

If this happens every week, the problem is no longer the plan. The press is the bottleneck, and a third shift or a second machine is worth considering.

How to sequence orders

  1. Orders whose date can’t move because the customer depends on it.
  2. Orders whose materials are already in stock.
  3. Orders that share a machine set-up and can run back to back.
  4. Everything else in order of promised date.

Grouping by set-up often saves more time than any other optimisation. Two orders using the same tool back to back save one tool change.

Keep a small buffer for rush orders. If the plan is 100% full, every rush order pushes another one out and the chain of delays begins.

Priority rules should be written down and known to everyone. Otherwise priority goes to whoever calls loudest, and the shop floor switches orders several times a day.

Materials are half the plan

A free machine with no material isn’t capacity. Before releasing an order, check that the materials in the BOM are in stock or when they arrive.

For materials with long lead times, a reorder point helps. It tells you when to order before the plan stops for lack of stock.

The check is simple if the BOM is right. Order quantity times the standard for each material is compared with available stock. Reserve the material for the order so another one doesn’t take it.

Plan versus actual, every day

The plan breaks on day one: a machine stops, someone is ill, a delivery is late. That’s normal. What isn’t normal is finding out at the end of the week.

A ten-minute meeting each morning does more than a long weekly report. What got done yesterday, what’s behind, what moves. Decisions go into the plan right away.

Reporting has to be quick for people on the shop floor. Started, finished, scrap. If reporting takes more than a minute, sooner or later it stops.

How we do it at Leanovix

In Leanovix, the production planning module gives every machine its capacity and efficiency, and ranks orders by a score you set: due date, priority, production hours. The queue shows what is late and by how many days. Work orders, BOM and shop floor reporting we build around your process, on request.

Frequently asked questions about production planning

How do you calculate production capacity?

Multiply productive hours per shift by the number of shifts and working days. Subtract breaks, set-ups and planned maintenance.

Can I plan production in Excel?

With a few machines and few orders, yes. When orders change daily and depend on materials, the spreadsheet stops showing the real date.

What is a bottleneck in production?

It’s the machine or team with the highest load. The whole shop can only produce as much as the bottleneck does.